Regional Rail Link
























Regional Rail Link

Melbourne RRL.png
Route of the Regional Rail Link in orange

Location
Melbourne
Proposer
Government of Victoria
Website
www.regionalraillink.vic.gov.au
Status
Completed
Type
Railway
Cost estimate
$3.65 billion
Start date
July 2009
Completion date
June 2015
Stakeholders
Government of Australia (major funding partner)
Government of Victoria (minor funding partner)
V/Line (operator)
Metro Trains Melbourne
Train travellers on Geelong, Bendigo and Ballarat lines
Opponents
Fair-go for Footscray Rail Residents

The Regional Rail Link (RRL) was a project to build a 47.5 kilometre length of railway through the western suburbs of Melbourne, Victoria, the main aim of which was to separate regional V/Line Ballarat, Bendigo and Geelong services from the electrified Melbourne suburban services, thereby increasing rail capacity and reliability. The project involved the building of an extra pair of tracks from Southern Cross station to Sunshine, parallel to the Western line, and a new double-track line from Deer Park, which joins with the Warrnambool line west of Werribee, near the site of the former Manor railway station. New stations were built at Tarneit and Wyndham Vale, while West Footscray and Sunshine stations were rebuilt. Additional platforms were built at Southern Cross and Footscray stations, and two level crossings near Sunshine were replaced by grade separations. The most used station before its construction, North Melbourne, was excluded from the project despite being the main connection hub for regional travellers not needing to go all the way to Southern Cross, and now requires regional rail link customers to change at Footscray.


The project was managed by the Regional Rail Link Authority, on behalf of the Victorian Government,[1] and, at the time, was the largest transport infrastructure project being undertaken in Australia.[2] Construction commenced in 2009 and was fully completed in June 2015, with the opening of the section of track from Manor junction to Deer Park West junction.


According to the 2012 PTV Network Development Plan, by December 2032 the RRL will be part of an electrified line from Grovedale, Geelong to South Yarra railway station, with a branch line to Avalon Airport, thereby integrating the Geelong line into the metropolitan system.[3]




Contents





  • 1 History

    • 1.1 Background


    • 1.2 Official status


    • 1.3 Baillieu government review



  • 2 Construction

    • 2.1 Timeline


    • 2.2 Route and achieved train speeds



  • 3 Impacts

    • 3.1 Cost and benefits


    • 3.2 Legacy


    • 3.3 Noise and pollution



  • 4 Lines


  • 5 Criticism


  • 6 See also


  • 7 References


  • 8 External links




History




New platforms at Footscray station in May 2014




Rebuilt West Footscray station in May 2014




Rebuilt Sunshine station in May 2014



Background


Following the rail infrastructure improvements provided by the Regional Fast Rail project, and subsequent growth in passengers and services, there was an increase in congestion in the Melbourne suburban area, where trains operated by V/Line shared tracks with Metro Trains Melbourne suburban trains, caused increasing delays on rail services.[4] late running by V/Line or metropolitan rail services affected the reliability of other trains, and V/Line trains, running express through most suburban stations, affected the timekeeping of stopping suburban trains. After major disruptions each operator might blame the other for causing the problem.[5][6]


A separate line for regional trains between Geelong and Melbourne, then called the "Tarneit Link", was included as a possible long-term rail option in the Bracks government's 2006 Meeting Our Transport Challenges report. Costed at around $500 million, the link was also recommended in Rod Eddington's East-West Link Needs Assessment study, released in April 2008.[7][8] By November 2008 the link between Deer Park and West Werribee was estimated to cost $1.5 billion.[9]



Official status


The project was expanded and re-branded as the Regional Rail Link when announced as part of the Brumby Government's Victorian Transport Plan of December 2008.[10] With a revised aim of separating all regional trains between Southern Cross and Geelong, Ballarat, and Bendigo, from suburban rail movements, the proposed route was from Southern Cross through Sunshine and Tarneit to West Werribee.


In May 2009 the project reached full funding, gaining the required allocation of $3.2 billion from the 2009 Federal budget, adding to funds to be provided by the Victorian Government.[11][12]


Several route options were investigated. One proposal involved the acquisition of up to 49 properties in Railway Place, Footscray to widen the existing railway corridor, and local residents launched a campaign against that proposal in May 2010.[citation needed] Other options floated were the sharing of tracks with freight trains in the existing Bunbury Street tunnel, or the construction of a second rail tunnel under Footscray[13] A preliminary route between Sunshine and Werribee was released for public consultation in June 2009.[14][15]


In July 2010, the final route through Footscray was announced by the state government.[16] Heading away from Melbourne, the pair of Regional Rail Link tracks run south of the current four suburban tracks until after the line has crossed the Maribyrnong River, where a new bridge was built. After crossing the river, the line passes over the top of the Newport bound suburban tracks on a flyover, and then runs between each pair of suburban tracks to Footscray station. At Footscray the line uses the existing platforms 1 and 2 (since renumbered 3 and 4), and then run on resumed land to the south of the suburban line to Sunshine, past Middle Footscray and West Footscray stations. Suburban trains towards Sunshine use the existing tracks except at Footscray, where two new platforms were built north of the four existing platforms.


To accommodate the final route, 26 homes and 84 businesses on Buckley Street, Footscray were acquired.[17] Many residents did not find out their homes were to be acquired until told by journalists, waiting up to 24 hours for official notification from Department of Transport representatives.[18] A Government spokeswoman said "every effort" had been made to contact the households affected, but bureaucrats had abandoned their planned visit to deliver the bad news because they did not want to be filmed by the media.[19] The proposals would also have acquired 136m² the heritage listed HV McKay Memorial Gardens, (Australia's oldest remaining industrial garden) as part of a grade separation along Anderson Road in Sunshine;[20] after community resistance and lobbying by Brimbank City Council, plans were altered to reduce the acquisition of the gardens to approximately 5m².[citation needed]



Baillieu government review


In February 2011, the incoming Baillieu government announced the project was under review, citing poor planning and a blow-out in costs. After the review, the Baillieu government estimated the price tag for the line to be $880 million more than stated by the outgoing Brumby government.[21] In November 2011, the secretary of the Victorian Department of Transport, Jim Betts, admitted that the lack of a mature plan, and the urgency of spending the money provided by the federal government as part of its economic stimulus package,[22] meant that there had been a rush to finalise the financial arrangements of the scheme. He commented that "the budget for that project was basically haggled over between the state and the commonwealth one weekend and we end up with a number written on the back of an envelope".[23]



Construction





Southern Cross station platforms 15 & 16 northern concourse entrance in December 2013


Construction commenced in August 2009.[24] The works were divided into seven packages - an overall railway signalling and control systems contract, and six sections of track:


  • signalling and control: consortium of UGL & Manidis Roberts[25]

  • Southern Cross station platforms 15 & 16: (overseen by Metro Trains Melbourne)[26]

  • Southern Cross station to Maribyrnong River (4.75 km): consortium of John Holland Group, Abigroup, Coleman Rail, AECOM & GHD[27][28]

  • Maribyrnong River to West Footscray station (2.35 km):

  • West Footscray to Deer Park West (13.4 km): consortium of Balfour Beatty, Parsons Brinckerhoff, Sinclair Knight Merz & Thiess[29]

  • Deer Park West to West Werribee Junction (25.5 km as a design and construct contract): Baulderstone & Leighton Contractors joint venture[30]

  • West Werribee Junction / Geelong Line interchange (approximately 1.5 km): Leighton Contractors & Downer EDI joint venture.[31][32]


Timeline


  • 2 July 2011: Construction begins, with the shifting of existing railway tracks between Sunshine and Tottenham[33][34]

  • 18 July 2011: Sydenham, Ballarat and Bendigo lines re-open after being closed for 2 weeks during the Victorian School Holidays to allow construction of the RRL[33]

  • Early 2013: fitout of platforms 15/16 at Southern Cross completed

  • 22 December 2013: platforms 15/16 at Southern Cross and approximately 5 kilometres of track from South Kensington opened[35]

  • 20 January 2014: new platforms 1/2 opened at Footscray

  • 28 April 2014: new platforms 3/4 opened at Sunshine[36]

  • 16 July 2014: commissioning of the new dedicated V/line tracks between South Kensington and Sunshine

  • 16 July 2014: new platforms 3/4 at Footscray opened

  • 6 October 2014: first test train operated on the new line via Tarneit[37]

  • 19 April 2015: originally scheduled opening of the new route and stations at Tarneit and Wyndham Vale, but delayed due to a lack of V/Line trains[38]

  • 21 June 2015: completion including opening of Tarneit and Wyndham Vale stations.[39]


Route and achieved train speeds


On 21 June 2015, a journey from Southern Cross Railway Station to Little River (and return) was undertaken with the intention of measuring the actual train speeds on that one journey. While that journey might not have been optimal or even typical, it gave an indication of the possible train speeds on the first day that Geelong-Melbourne trains ran on the Regional Rail Link.


On the outbound journey, the following speeds were achieved:[40]


  • Southern Cross to Footscray Station: up to 40 km/h

  • Footscray Station to Sunshine Station: up to 105 km/h

  • Sunshine to West Werribee junction with original Geelong Line: up to 160 km/h.

On the return journey from Little River to Southern Cross station, the following speeds were achieved:[41]


  • New Track - West Werribee to Deer Park - 160 km/h

  • Junction of RRL and Ballarat rail lines to Sunshine Railway Station - 130 km/h

  • Sunshine Railway Station to near Currajong Street, West Footscray - 130 km/h

  • Currajong Street to Footscray Station - 80 km/h

  • Footscray Station to Lloyd Street underpass - 80 km/h

  • Lloyd St underpass to Southern Cross Station - 40 km/h.


Impacts



Cost and benefits


In May 2010, the estimated cost was $4.3 billion, and economic benefits were estimated to be $6.2 billion.[42]


In April 2011 the incoming Baillieu government stated it would cost closer to $5 billion and two years longer to build.[43] In July 2011 the cost was estimated at $5.3 billion with a completion date of 2016.[33]


In the 2015/16 State Budget the final cost of the project was given as $3.65 billion, down from the previous estimate of $4.1 billion.[44]


However, the final cost of property acquisitions related to the project will not be fully known until December 2018, so this cost estimate may increase. [45]



Legacy


All passenger trains on the Ballarat, Bendigo and Geelong lines use the Regional Rail Link to and from Melbourne, removing the capacity problems and potential conflicts encountered when these services shared tracks with metropolitan trains, which are themselves heavily loaded.[46] The link allows more regional and metropolitan trains to run, which, combined with the purchase of new rolling stock,[47][48] has helped alleviate peak hour overcrowding on regional services, particularly those from Geelong and Ballarat, and freed up capacity on Melbourne suburban tracks to allow more trains to run. To some extent though, patronage from outer suburban stations like Tarneit and Wyndham Vale have put pressure on the services, and time saved may have been marginal or not even existent.[49] The Public Transport Users Association claimed travel times between Melbourne and Geelong might increase by 10 minutes.[50]


As part of the project, the partially-built platforms 15 and 16 at Southern Cross station were completed, which increased the number of trains the station can handle. However, no platforms were provided for RRL trains at North Melbourne station, which was a major interchange point for regional passengers using northern suburban and City Loop trains, as well as the recently-introduced Route 401 bus from North Melbourne to the hospital and university precincts. No reason was given for that decision, and after the RRL opened, passengers wanting to get to North Melbourne had to alight at Footscray or Southern Cross stations and catch another train.



Noise and pollution


Controversy emerged with the release of reports from the Victorian Environmental Protection Agency (EPA) which criticized the methodology and results contained in assessments submitted by the RRL team to former state planning minister, Justin Madden, as part of the project planning referral. The EPA reports state, "in Footscray, for the most exposed residents, a vast majority of the population will experience chronic noise-induced sleep disturbance, with very significant proportions highly disturbed... For the most exposed residents in other areas, almost half the community will experience chronic noise-induced sleep disturbance." The reports also raised concerns about the Footscray Park Railway Reserve where, the EPA predicted, the public would be exposed to dangerous levels of nitrogen dioxide from increased diesel train traffic. The EPA noted that planned risk assessments had not been done by the Department of Transport.[51] Madden had viewed the EPA reports in September 2010, but ruled that an Environment Effects Statement (EES) was not required for Section-1 of the RRL project.[52]



Lines


.mw-parser-output .RMboxbox-shadow:0 2px 2px 0 rgba(0,0,0,.14),0 1px 5px 0 rgba(0,0,0,.12),0 3px 1px -2px rgba(0,0,0,.2).mw-parser-output .RMinlinefloat:none;width:100%;margin:0;border:none.mw-parser-output table.routemappadding:0;border:0;border-spacing:0;background:transparent;white-space:nowrap;line-height:1.2;margin:auto.mw-parser-output .RMirborder:0;border-spacing:0;display:table;line-height:0;padding:0!important;margin:0 auto!important.mw-parser-output table.routemap .RMsidisplay:inline;font-size:90%.mw-parser-output table.routemap .RMl1padding:0 3px;text-align:left.mw-parser-output table.routemap .RMr1padding:0 3px;text-align:right.mw-parser-output table.routemap .RMltext-align:right.mw-parser-output table.routemap .RMrtext-align:left.mw-parser-output table.routemap .RMl4padding:0 3px 0 0;text-align:left.mw-parser-output table.routemap .RMr4padding:0 0 0 3px;text-align:right.mw-parser-output table.routemap>tbody>trline-height:1.mw-parser-output table.routemap>tbody>tr>tdpadding:0;width:auto;vertical-align:middle;text-align:center.mw-parser-output .RMir>tbody>trdisplay:inline-table.mw-parser-output .RMir>tbody>tr>tdpadding:0;height:20px;min-height:20px.mw-parser-output .RMir .RMovposition:relative.mw-parser-output .RMir .RMicposition:absolute;left:0px;top:0px;padding:0.mw-parser-output .RMir .RMtxline-height:20px;vertical-align:middle;text-align:center.mw-parser-output .RMir .RMspheight:20px;min-height:20px.mw-parser-output .RMir div>.RMtxposition:absolute.mw-parser-output .RMir .RMtx>abbr,.mw-parser-output .RMir .RMtx>divline-height:.975;display:inline-block;vertical-align:middle.mw-parser-output .RMir .RMf_height:5px;min-height:5px;width:20px;min-width:20px.mw-parser-output .RMir .RMfmheight:100%;min-height:100%;width:4px;min-width:4px;margin:0 auto.mw-parser-output .RMir .RMowidth:2.5px;min-width:2.5px.mw-parser-output .RMir .RMcwidth:5px;min-width:5px.mw-parser-output .RMir .RMocwidth:7.5px;min-width:7.5px.mw-parser-output .RMir .RMdwidth:10px;min-width:10px.mw-parser-output .RMir .RModwidth:12.5px;min-width:12.5px.mw-parser-output .RMir .RMcdwidth:15px;min-width:15px.mw-parser-output .RMir .RMocdwidth:17.5px;min-width:17.5px.mw-parser-output .RMir .RM_width:20px;min-width:20px.mw-parser-output .RMir .RM_owidth:22.5px;min-width:22.5px.mw-parser-output .RMir .RM_cwidth:25px;min-width:25px.mw-parser-output .RMir .RM_ocwidth:27.5px;min-width:27.5px.mw-parser-output .RMir .RM_dwidth:30px;min-width:30px.mw-parser-output .RMir .RM_odwidth:32.5px;min-width:32.5px.mw-parser-output .RMir .RM_cdwidth:35px;min-width:35px.mw-parser-output .RMir .RM_ocdwidth:37.5px;min-width:37.5px.mw-parser-output .RMir .RMbwidth:40px;min-width:40px.mw-parser-output .RMir .RMcbwidth:45px;min-width:45px.mw-parser-output .RMir .RMdbwidth:50px;min-width:50px.mw-parser-output .RMir .RMcdbwidth:55px;min-width:55px.mw-parser-output .RMir .RM_bwidth:60px;min-width:60px.mw-parser-output .RMir .RM_cbwidth:65px;min-width:65px.mw-parser-output .RMir .RM_dbwidth:70px;min-width:70px.mw-parser-output .RMir .RM_cdbwidth:75px;min-width:75px.mw-parser-output .RMir .RMswidth:80px;min-width:80px.mw-parser-output .RMir .RMdswidth:90px;min-width:90px.mw-parser-output .RMir .RM_swidth:100px;min-width:100px.mw-parser-output .RMir .RM_dswidth:110px;min-width:110px.mw-parser-output .RMir .RMbswidth:120px;min-width:120px.mw-parser-output .RMir .RMdbswidth:130px;min-width:130px.mw-parser-output .RMir .RM_bswidth:140px;min-width:140px.mw-parser-output .RMir .RM_dbswidth:150px;min-width:150px.mw-parser-output .RMir .RMwwidth:160px;min-width:160px.mw-parser-output .RMir .RM_wwidth:180px;min-width:180px.mw-parser-output .RMir .RMbwwidth:200px;min-width:200px.mw-parser-output .RMir .RM_bwwidth:220px;min-width:220px.mw-parser-output .RMir .RMswwidth:240px;min-width:240px.mw-parser-output .RMir .RM_swwidth:260px;min-width:260px.mw-parser-output .RMir .RMbswwidth:280px;min-width:280px.mw-parser-output .RMir .RM_bswwidth:300px;min-width:300px

Regional Rail Link


Legend








































































































0 km


Southern Cross (SSS)

Zone 1



























6.1km


Footscray (FSY)

Zone 1


















13.5km


Sunshine (SUN)

Zone 1 & 2










Standard Gauge to Albury









Sunbury/Bendigo/Swan Hill/Echuca lines









15.02km


Ardeer(APR)

Zone 2










20.82km


Deer Park (DEK)

Zone 2










Ballarat/Ararat/Melton lines




















Tarneit (TNT)

Zone 2











Wyndham Vale (WVL)

Zone 2


















← Geelong line →








Criticism


Despite the immediate advantage to commuters in the Wyndham Vale and Tarneit areas, there has been some disappointment regarding the irregular spacing of services at these stations. For example, on Monday to Friday morning services, there is a 26-minute gap between the 8:42 AM and the 9:08 AM city-bound trains at Tarneit Station.[53]


Ballarat line passengers have been particularly upset about their services since the full opening of the RRL. Due to a rolling stock shortage, some Ballarat trains had fewer carriages than before, and timekeeping of services worsened, despite the promise of greater reliability after the RRL opened.[54]


Following the opening of the Regional Rail Link, V/Line trains on the Ballarat line failed to meet punctuality targets for 14 consecutive months.[55]


In May 2018, the Victorian Auditor-General completed an audit on the Regional Rail Link, titled "Assessing Benefits from the Regional Rail Link Project" [56]


While acknowledging that the project has had significant benefits, some of these unexpected, the Auditor-General slammed the State Government's of the time, the former Victorian Department of Transport and the Regional Rail Link Authority for its mismanagement of the project, particularly in it's planning stages. [57]


He cited that the lack of any sort of formal business case into the project, made it extremely difficult to determine just what the benefits of the project were meant to be, and whether or not RRL had lived up to the expectations set for it when the project was funded in 2009. He also said that planners had not adequately predicted just how many people would use RRL upon its opening, thus the line's designed maximum capacity of 18 trains per-hour would make it difficult to add the required amount of services in the future. [58]





See also



  • Southern Sydney Freight Line – a similar project in Sydney separating suburban and freight services


References




  1. ^ Peter Begg (26 April 2011). "Regional rail link to go ahead". Geelong Advertiser. Retrieved 2012-05-06. 


  2. ^ Australia's largest public transport project leaps ahead Premier of Victoria 21 December 2011


  3. ^ "Network Development Plan – Metropolitan Rail" (PDF). Public Transport Victoria. December 2012. Retrieved 2017-07-06. 


  4. ^ Jason Dowling & Natalie Puchalski (6 June 2009). "Regional rail travel booming, despite delays". The Age. Retrieved 2009-06-19. 


  5. ^ Mex Cooper (11 May 2009). "Geelong, V/Line Connex rail delays after fuel spill". The Age. Melbourne. Retrieved 2009-06-19. 


  6. ^ Mex Cooper (14 January 2009). "Melbourne train commuters warned of more delays". The Age. theage.com.au. Retrieved 2009-06-19. 


  7. ^ Royce Millar & Clay Lucas (29 March 2008). "West may get new rail line". The Age. Melbourne: www.theage.com.au. Retrieved 2009-06-19. 


  8. ^ Rod Eddington (March 2008). "Fact sheet - Recommendations". East West Links Needs Assessment final report. www.transport.vic.gov.au. Retrieved 2009-06-19. 


  9. ^ Clay Lucas (3 November 2008). "Planned $1.5bn rail link will free up bottlenecks". The Age. Melbourne: www.theage.com.au. Retrieved 2009-06-19. 


  10. ^ Regional Rail Link to Streamline Train Services Premier of Victoria 8 December 2008


  11. ^ Regional Rail Work to Start this Year after $4 Billion Project Secures Federal Funding Premier of Victoria 14 May 2009


  12. ^ Mex Cooper (18 May 2009). "Tough decisions necessary: PM". The Age. Melbourne. Retrieved 2009-06-19. 


  13. ^ Clay Lucas (7 May 2010). "Rail plan with at least one obstacle: Footscray". The Age. Melbourne: theage.com.au. Retrieved 2010-05-07. 


  14. ^ Clay Lucas (16 June 2009). "New train line and ring road routes to be unveiled". The Age. Melbourne. Retrieved 2009-06-19. 


  15. ^ Proposed Route of Regional Rail Link Revealed Premier of Victoria 17 June 2009


  16. ^ "Houses to go for new regional rail link". The Age. Melbourne: theage.com.au. 12 July 2010. Retrieved 2010-07-16. 


  17. ^ "Footscray residents slam plans to acquire homes for transport upgrade". Herald Sun. Retrieved 2010-07-16. 


  18. ^ Robyn Grace (13 July 2010). "Rail demolition: Footscray residents fume over notification blunder". The Age. Melbourne. Retrieved 2010-07-16. 


  19. ^ Clay Lucas (13 July 2010). "Residents not told their homes will go". The Age. Melbourne. Retrieved 2010-07-16. 


  20. ^ Laura Wakely (14 February 2012). "No Opportunity". Star Community. Retrieved 27 April 2015. 


  21. ^ Gough, Deborah (13 February 2011). "Fears review of rail link scandal may be tainted". The Age. Melbourne. 


  22. ^ "Brumby rapt at $3bn boost for rail link". The Age. 2009-05-13. Retrieved 2015-08-25. 


  23. ^ Jason Murphy (2011-11-16). "Vic project railroaded". Australian Financial Review. Retrieved 2012-07-24. 


  24. ^ Construction Starts on the $4.3 Billion Regional Rail Link Premier of Victoria 27 August 2009


  25. ^ Rail Systems Regional Rail Link


  26. ^ Southern Cross Regional Rail Link


  27. ^ New contract moves Regional Rail Link into high gear Premier of Victoria 12 May 2012


  28. ^ City - Maribyrnong River Regional Rail Link


  29. ^ Footscray - Deer Park Regional Rail Link


  30. ^ Deer Park - West Werribee Junction Regional Rail Link


  31. ^ Full steam ahead on the Regional Rail Link Premier of Victoria 8 June 2012


  32. ^ West Werribee Junction Regional Rail Link


  33. ^ abc "Commuters face snarls as $5.3bn rail project digs in". The Age. Melbourne. 4 July 2011. 


  34. ^ Regional Rail Link works to kick off in July Premier of Victoria 17 May 2011


  35. ^ Platforms 15 and 16 Regional Rail Link


  36. ^ "Ballarat services now stopping at new, dedicated platforms at Sunshine station" Railway Digest June 2014 page 21


  37. ^ "First RRL test train was an N class light engine for signal sighting trials". Wongm's Rail Gallery. Melbourne. 6 October 2014. 


  38. ^ "Andrews government delays Regional Rail Link opening by two months". The Age. Melbourne. 20 February 2015. 


  39. ^ Geelong and Warrnambool trains to run via Regional Rail Link from 21 June 2015 V/Line


  40. ^ https://www.strava.com/activities/329663048


  41. ^ https://www.strava.com/activities/329678438


  42. ^ Lucas, Clay (22 May 2010). "Cost won't put a stop to freeway: Brumby". Melbourne: The Age. 


  43. ^ "Rail link delay as bill nears $5bn". The Age. Melbourne. 5 April 2011. 


  44. ^ "Relief from commuter crush years away despite billions in budget". The Age. Melbourne. 5 May 2015. 


  45. ^ https://www.audit.vic.gov.au/report/assessing-benefits-regional-rail-link-project


  46. ^ Lucas, Clay (21 March 2009). "Melbourne's Big Squeeze". The Age. Retrieved 2009-05-15. 


  47. ^ "Bombardier Awarded Contract for a Further 32 DMU Cars for V/Line Passenger in Australia". Bombardier. Retrieved 2012-12-16. 


  48. ^ "Coalition Orders 40 New Carriages for V/Line". Department of Transport. 26 November 2012. Retrieved 2012-12-16. 


  49. ^ Lucas, Clay (2010-06-15). "$4.3b link won't cut travel times". The Age. Retrieved 2017-07-06. 


  50. ^ "Users ask the government how much slower the new rail link to Geelong will be". Public Transport Users Association. Retrieved 25 January 2014. 


  51. ^ Deborah Gough & Melissa Fyfe (6 February 2011). "Residents face lost sleep over rail project". The Age. The Sunday Age. Melbourne. 


  52. ^ Minister for Planning (7 October 2010). "Reasons for Decision Under Environmental Effects Act 1978 : Regional Rail Link 1 – Moonee Ponds Creek to Deer Park". Department of Planning and Community Development. DPCD. 


  53. ^ "V/Line Geelong Line" (PDF). Public Transport Victoria. 27 June 2016. Retrieved 23 May 2016. 


  54. ^ Schetzer, Alana (2015-08-08). "Ballarat train commuters suffer after Regional Rail Link opens". The Age. Retrieved 2015-08-26. 


  55. ^ https://www.vline.com.au/About-V-Line/Additional-pages/Past-performance


  56. ^ https://www.audit.vic.gov.au/report/assessing-benefits-regional-rail-link-project


  57. ^ https://www.audit.vic.gov.au/report/assessing-benefits-regional-rail-link-project


  58. ^ https://www.audit.vic.gov.au/report/assessing-benefits-regional-rail-link-project



External links


  • YouTube video overview of works Public Transport Victoria





The name of the pictureThe name of the pictureThe name of the pictureClash Royale CLAN TAG#URR8PPP

Popular posts from this blog

Top Tejano songwriter Luis Silva dead of heart attack at 64

政党

天津地下鉄3号線